Kelantan Crown Prince Tengku Muhammad Fakhry Petra (right) is briefed by Malaysia Rail Link Sdn Bhd CEO Datuk Seri Darwis Abdul Razak during his visit to the ECRL station’s site in Bandar Baru Tunjong, Kota Bharu, Kelantan on June 23, 2024. — Picture by BERNAMA

ECRL project in Kelantan reaches 79 pct progress, remains on schedule

KOTA BHARU, June 24 — The construction of the East Coast Railway Link (ECRL) in Kelantan covering 43 kilometres has reached a progress of 79.81 per cent as of last month, said Malaysia Rail Link Sdn Bhd (MRL) chief executive officer Datuk Seri Darwis Abdul Razak.

He said the progress aligns with the project schedule for the expected completion of the railway line from Kota Bharu to Terminal Bersepadu Gombak (integrated transport terminal).

He said Kelantan would have a passenger station (Kota Bharu Station) in Bandar Baru Tunjong and Pasir Puteh Station in Kampung Cherang Tuli for passengers and cargo.

He mentioned that the Kota Bharu Station, which is under construction, will have multiple platforms and be equipped with parking spaces, pick-up and drop-off locations, covered walkways, workers’ quarters, and a landscape site, among other things.

He said this in a statement issued in conjunction with the visit by Kelantan Crown Prince Tengku Muhammad Fakhry Petra to the ECRL station’s site in Bandar Baru Tunjong, here yesterday.

Darwis said the Kota Bharu Station will feature the ‘Rumah Meleh Melayu’ and ‘Bunga Ketam Guri’ design concepts and other unique characteristics of Kelantan culture.

Tengku Muhammad Fakhry was briefed on the project’s progress before visiting the railway site.

Also present were state Public Works, Infrastructure, Water and Rural Development Committee chairman Datuk Izani Husin and Kelantan police chief Datuk Muhamad Zaki Harun.

Transport Minister Anthony Loke Siew Fook was quoted as saying that he is confident that the ECRL project would be completed according to schedule in December 2026 and operational starting Jan 2027.

The 665-km ECRL project costing RM50.27 billion will connect Kota Bahru with the Gombak integrated transport terminal, cutting travel time to four hours from seven hours by road or over 12 hours during festive seasons.

— Bernama

Top Picks

Wai Ching sets new record en route to defending MBPJ Tower Run title

Commendable achievement despite dip in gold medal haul for squash — SRAM

Vietnam to develop extensive undersea cable network by 2030