Puchong landslide: Piles to be installed in four days, ahead of schedule

PUCHONG, Dec 20 — Works to install piles to stabilise soil movement in the landslide area along Jalan Wawasan in Taman Wawasan, here, is expected to be completed within four days.

Subang Jaya City Council Mayor Datuk Mohd Fauzi Mohd Yatim said to date, a total of 121 out of the 375 piles have been placed.

“After the installation of the iron piles is completed, the process of restoring the slope to its original structure will be carried out before proceeding with road leveling works,” he told Bernama at the incident control post here today.

Previously, on December 17, it was reported that the installation of the iron piles would take approximately two weeks to be completed.

Meanwhile, Fauz said the cause of the landslide, which struck on Saturday, is still being investigated by the Minerals and Geoscience Department.

The occupants of nine terraced houses in the residential area were ordered to evacuate following the landslide.

— Bernama

Top Picks

Sultan, MB condemn acid attack on Faisal Halim, want immediate police action

Editor Selangor Journal

KKB by-election early voting tomorrow

Hannah Yeoh urges greater access to sports for Orang Asli